House #15-glazing is in progress
Houses #13-14-under the roof
Houses #11-12-block filling - 1st floor, columns and ceiling 2nd floor;
Houses #9-10-blocks - 1st floor, columns-2nd floor
Houses #7-8-columns and overlap of the 1st floor
Houses #5-6-Foundation and columns of the 1st floor
House #3-4 - the Foundation
Houses # 1-2-prepared for filling the Foundation.